Blower Relocation for Pureflo 6 STP
Moving the blower on a Pureflo 6 Sewage Treatment Plant into a cabinet externally of the plant.
The original blower was located under the green lid which is in the plant. This meant the blower is affected from the humidity within the treatment zone; and in this case when the clients outlet failed the blower got flooded and tripped the electrics out.
With the blower now moved externally from the plant into a waterproof box this problem was now solved and a new JDK blower was also installed.